PNP Bare schedule of Processing

NOTE: list of sched below are subject to change means tentative.

March 2 to 27 - ADHOC

March 30 to 31 - folders will be submitted to the regional headquarters from the PPOs/OCPO

April 1 to 9 - Physical Agility Test (PAT)

April1 to May 22 - Complete background examination

April 13 to 14 - written examination

April 15 to 17 - Neoro-Phych

April 21 to 23 - Drug Test

April 27 to May 22 - physical/medical and dental exam

May 25 to 29 - PRO screening Committee interview

June 1 to 4 - final screening committee deliberation

June 5 - publish the interview results

June 8 to 12 - Submission of Resolution /folders to NAPOLCOM for confirmation

June 22 to 26 - submission to the Civil Service Commission (CSC) for attestation of appointment

June 29 to 30 - and approval of appointment by the Police Regional Office (PRO) Director

July 1 - oath taking of successful applicants